Providence Station renovation

Proposed Stage: proposed

Newest evidence 2026-10-06.

State of Good Repair and Capacity Project: construction began fall 2024 on a roughly two-year schedule; every official source gives 2026 for completion, and RIDOT said on March 3, 2026 that the work would be complete this year. No completion announcement found as of October 6, 2026; RIDOT's project page still gives 2026. About $30M: $12.5M FRA grant, $9.75M Amtrak, $7.75M RIDOT. Amtrak owns the station. S12 S12b R8 R9

On the list because the city has proposed it. Not yet verified by the author.

Years out

0 years out

Stated for 2026 by RIDOT in March 2026; not yet verified.

What it needs first